Issue - decisions

Bulmershe New Build V2

30/11/2017 - Bulmershe New Build

That:

 

1)        having considered the range of options for the future provision of Leisure facilities at Bulmershe the following option be approved:

 

Option E to consist of: A newly built leisure centre with a 4 badminton court sports hall; 25m x 6 lane swimming pool; a 75 Station gym; and 2 Studios, teaching pool with movable floor and Café;

 

2)        authority be delegated to the Director of Corporate Services and Executive Member for Environment, Sports, Environmental Health, Leisure and Libraries to approve the detailed options for the scheme;

 

3)         an additional Capital budget of £4.54 million be approved; 

 

4)        it be noted that the revenue cost of all borrowing (including the additional £4.54m) will be funded by the income generated by the facility.