93 Capital Monitoring 2016/17 - end of December 2016 PDF 138 KB
Additional documents:
Decision:
That:
1) the Capital Monitoring report for 3rd quarter of 2016/17, as set out in Appendix A to the report, be noted;
2) the release of £1,600k originally profiled in the Medium Term Financial Plan for 2017/18 into 2016/17, due to acceleration in the build of Arborfield Secondary School, be approved.
Minutes:
The Executive considered a report setting out the position of the Capital budget as at the end of December 2016; which showed a £164k underspend variance forecast against budget.
RESOLVED That:
1) the Capital Monitoring report for 3rd quarter of 2016/17, as set out in Appendix A to the report, be noted;
2) the release of £1,600k originally profiled in the Medium Term Financial Plan for 2017/18 into 2016/17, due to acceleration in the build of Arborfield Secondary School, be approved.