Capital Monitoring 2020/21 - end of September 2020

Meeting: 29/10/2020 - Executive (Item 41)

41 Capital Monitoring 2020/21 - end of September 2020 pdf icon PDF 302 KB

Additional documents:

Decision:

That:

 

1)        it be noted that the Council’s Capital Programme has been reviewed and will continue to be throughout the year in the context of the impact of Covid-19 on funding sources and service requirements, and that any changes will be presented to Executive for approval;

 

2)        the proposed rephasing to the Capital Programme following the ‘in-year’ review including the impact of Covid 19, as set out in paragraph 3 and Appendix B, be noted and approved. There is no financial / service impact from the reprofiling of budgets into 2021/2022;

 

3)        the position of the capital programme at the end of Quarter 2 (to 30thSeptember 2020) as summarised in the report and set out in detail in Appendix A be noted;

 

4)        Appendix C, which highlights capital performance by key activities, be noted. This is part of the Councils enhanced financial management focusing on the key capital projects, monitoring performance against budget and impact on funding levels (including borrowing);

 

5)        it be agreed that £6m of ringfenced funded capital budget, originally programmed for 2021/2022, is brought forward into the current year (2020/2021), for the acceleration of the delivery of the SCAPE Road Infrastructure project;

 

6)        an addition to the 2020/21 capital programme, the project for Church Lane, Shinfield Flood Alleviation Scheme, to be funded from ring fenced Flood and Coastal Erosion Risk Management (FCERM) grant from the Environment Agency of £115k be noted and approved.

Minutes:

The Executive considered a report setting out the Capital budget position as at the end of September 2020.

 

The Executive Member for Finance and Housing introduced the report and highlighted changes from the previous quarter.  These included bringing forward, from 2021/2022 into the current year, £6m of ringfenced funds to pay the Council’s contribution to the Winnersh Relief Road and the addition of a flood alleviation scheme for Church Lane, Shinfield to be funded from a £115k ring fenced grant from the Environment Agency.

 

RESOLVED that:

 

1)        it be noted that the Council’s Capital Programme has been reviewed and will continue to be throughout the year in the context of the impact of Covid-19 on funding sources and service requirements, and that any changes will be presented to Executive for approval;

 

2)        the proposed rephasing to the Capital Programme following the ‘in-year’ review including the impact of Covid-19, as set out in paragraph 3 and Appendix B, be noted and approved. There is no financial / service impact from the reprofiling of budgets into 2021/2022;

 

3)        the position of the capital programme at the end of Quarter 2 (to 30thSeptember 2020), as summarised in the report and set out in detail in Appendix A, be noted;

 

4)        Appendix C, which highlights capital performance by key activities, be noted. This is part of the Councils enhanced financial management focusing on the key capital projects, monitoring performance against budget and impact on funding levels (including borrowing);

 

5)        it be agreed that £6m of ringfenced funded capital budget, originally programmed for 2021/2022, is brought forward into the current year (2020/2021), for the acceleration of the delivery of the SCAPE Road Infrastructure project;

 

6)        an addition to the 2020/21 capital programme, the project for Church Lane, Shinfield Flood Alleviation Scheme, to be funded from ring fenced Flood and Coastal Erosion Risk Management (FCERM) grant from the Environment Agency of £115k be noted and approved.