Decision Maker: Executive
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
To consider the Capital monitoring position at the end of quarter 2
That:
1) the proposed rephasing to the Capital Programme following the ‘in-year’ review, as set out in paragraph 3 and Appendix B, be noted and approved. There is no financial / service impact from the reprofiling of budgets into 2022/2023;
2) the position of the Capital Programme at the end of Quarter 2 (to 30 September 2021), as summarised in the report below and set out in detail in Appendix A, be noted;
3) the successful application for external funding of £98k, for allocation to new capital schemes to put in place a heat decarbonisation plan for four Leisure Centres, Bulmershe Secondary School and Waterford House (as set out in paragraph 7 of the report) be noted.
Wards Affected: None Specific;
Declarations: None
Dispensations: None
Reference Number: WBC1230
Contact: James Sandford Email: james.sandford@wokingham.gov.uk Tel: 0118 974 6577.
Report author: James Sandford
Publication date: 28/10/2021
Date of decision: 28/10/2021
Decided at meeting: 28/10/2021 - Executive
Accompanying Documents: